Venice Place Project

Final Environmental Impact Report

 

Environmental Case No.
2016-4321-EIR
State Clearinghouse No.
2016061033

 

Project Address: 1021, 1021 ½, 1023, 1023 ½, 1025, 1027, 1029 ½, 1031, 1033, 1047, 1049, and 1051 South Abbot Kinney Boulevard, 1011 Electric Avenue, Los Angeles, CA 90291

Community Plan Area: Venice

Council District: 11, Bonin

PROJECT DESCRIPTION:

The site currently contains 12,560 square feet of existing development comprised of three restaurants totaling 7,444 square feet, a 1,572 square-foot private school, 3,544 square feet of office space (of which 1,344 square feet will be retained), 2,963 square feet of existing outdoor landscaped area used as a retail nursery (the Sculpture Garden), and a 60-space surface parking lot. 

The project proposes the demolition of one 2,442 square-foot restaurant, the existing private school, 2,200 square feet of office space, and the surface parking lot; and the construction, use, and maintenance of a 70,310 square-foot, mixed-use development (includes existing and new floor area). The mixed-used development is comprised of two existing restaurants and a new 3,810 square-foot hotel restaurant having 2,514 square-feet of Service Floor area, a new Apartment Hotel with four dwelling units and 78 guest rooms, 2,935 square feet of ground floor retail space including a market with 170 square feet of Service Floor area, a 1,735 square-foot spa, and 2,027 square feet of office use. The project will construct three (3) new three-story mixed-use buildings, each with a maximum of 30 feet in height, and one (1) new two-story building, approximately 25 feet in height; all new structures are connected by pedestrian bridges. The project provides a total of 175 parking spaces, at grade and within three subterranean levels and will provide an on-street loading area on Broadway, limiting the use of the space for loading during the hours of 7:00 A.M. to 6:00 P.M. Monday through Friday and 10:00 A.M. to 4:00 P.M. on Saturday; a loading zone is also provided onsite. The project also requires excavation, grading, and approval of a haul route for the export of approximately 24,591.65 cubic yards of dirt.

FILE REVIEW:

The complete file including the Final Environmental Impact Report (FEIR) or the documents referenced in the EIR are available for public inspection between the hours of 8:30 a.m. to 4:00 p.m., Monday through Friday. Please call or email the staff identified on the front page, at least three (3) days in advance to assure that the files will be available. The Final EIR is also available online at the Department of City Planning’s website at http://planning.lacity.org (click on the “Environmental Review” tab on the left-hand side, then “Final EIR”, and click on the Project title); and copies if the FEIR are also available at the following Library Branches:

Los Angeles Central Library, 630 West 5th Street, Los Angeles, CA 90071
Venice-Abbot Kinney Memorial Branch, 501 Venice Boulevard, Los Angeles, CA 90291
Mar Vista Branch, 12006 Venice Boulevard, Los Angeles, CA 90066

The Final EIR can also be purchased on CD-ROM for $5.00 per copy. Contact Adam Villani at (213) 847-3688 to purchase copies.


Please direct your comments to:
           

Via Mail:        Adam Villani
                        City of Los Angeles, Department of City Planning
                        221 N. Figueroa Street, Suite 1350
                        Los Angeles, CA 90012
                        
 Via Email:      Adam.Villani@lacity.org

Puede obtener información en Español acerca de esta junta llamando al (213) 978-1454.

 

Final Notice of Public Hearing

Final EIR Sections


Final EIR Appendix